Below is a list of miscellaneous construction and renovation projects Tufts will be undertaking this Summer. These projects tend to be short in length and small in scope. A brief summary is provided, and any further project-specific questions can be directed to the indicated Project Manager. General questions, comments, and concerns related to Tufts’ construction activity can be directed to construction@tufts.edu.

Campus
Project
Project Manager
Medford  Bed Optimization  Ray Santangelo
This interior renovation product involves adding beds to dorm rooms to change single bed rooms into double bed rooms and double bed rooms into triple bed rooms. This renovation applies to Metcalf Hall, Richardson House, Hodgdon Hall, West Hall, Commuter House, Hill Hall and Wren Hall. For any questions, please contact Ray Santangelo at raymond.santangelo@tufts.edu.

Bed Optimization Summer Project

Medford  Learning Spaces  Ray Santangelo
This is an interior renovation project focusing on classroom upgrades, AV updates, lighting changes and furniture replacement. The affected areas are Sophia Gordon Hall, three rooms in Cabet Hall, Anderson 208, 4 Colby 136, and Tisch 316. For any questions, please contact Ray Santangelo at raymond.santangelo@tufts.edu.

Learning Spaces Summer Project

Medford Miner Paige Windows Ray Santangelo
The windows will be replaced in both Miner Hall and the Crane Room in Paige Hall. It is expected that the replacement process will be completed by the first week of August of 2017. For any questions, please contact Ray Santangelo at raymond.santangelo@tufts.edu.

Miner Hall Window Replacement Summer Project

Medford Roof Replacement  Ray Santangelo
For this external renovation project the roofs of Latin Way and 4 Colby A will be replaced. The replacement process will start the week of June 10th and is expected to be completed by the end of September of 2017/the beginning of August of 2017. For any questions, please contact Ray Santangelo at raymond.santangelo@tufts.edu.
Medford Electrical Segregation  Ray Santangelo
This internal and external renovation aims to add a larger building for stand-by power and replace the fire alarm systems. This project will involve the Sci-Tech building on 4 Colby Street. The renovation is expected to be completed by the end of January 2018 For any questions, please contact Ray Santangelo at raymond.santangelo@tufts.edu.
Medford Timko  Ray Santangelo
This internal renovation project involves the modification of two existing spaces in 4 Colby in regards to the Chemical Vapor Disposition (CVD) lab. The rooms will be used for research space. The renovation is expected to begin in August of 2017 and be completed by January 2018. For any questions, please contact Ray Santangelo at raymond.santangelo@tufts.edu.
Medford 520 Boston Ave Exterior Ray Santangelo
This interior and exterior renovation will update 520 Boston Ave. For the exterior a new facade will be created for the building. The interior of the building will be gutted and renovated for the Facilities Services office, Residential Facilities office, and the Capital Programs office. For any questions, please contact Ray Santangelo at raymond.santangelo@tufts.edu.
Medford TAB Basketball Court Ray Santangelo
An internal renovation project is set for the basketball court at the Tufts Administration Building (TAB) in Davis Square. The entire court and playing area including the hoops, floor, and other court components will be replaced. This renovation is expected to be completed by the end of October of 2017. For any questions, please contact Ray Santangelo at raymond.santangelo@tufts.edu.
Medford Haskell Hill John Crow
Haskell Hall is having its exterior masonry renovated. Alongside the change in its outward appearance, there are also limited interior modifications being made in Haskell Hall related to the windows and to the electrical system. This renovation began in late May and is expected to be completed by the middle of August of 2017. For any questions, please contact John Crow at john.crow@tufts.edu.
Medford  Cousins Gym/Ellis Oval Taylan Ekici
Cousins Gym is undergoing an internal renovation with a floor refinish. Similarly the Ellis Oval is being renovated with new sod-turf. Both of these changes should be completed by the end of the summer 2017 to allow for use by new and returning students at the beginning of the school year. For any questions, please contact Taylan Ekici at taylan.ekici@tufts.edu.