Construction Update
Week of 4/20/17

  • The Henry and Lois Foster Hospital for Small Animals is complete. This includes the main entrance, lobby, examination rooms, specialty care rooms, an isolation suite, conference rooms, and a reflection room.
  • For photos and further information see TuftsNow

 

Construction Update
11
/16

  • The lobby and examination rooms are open for use.
  • Some conference rooms are complete.

FSHA Reception Desk FSHA Reception Desk

FSHA New Main Entrance

FSHA New Main Entrance

FSHA New Reception Area

FSHA Reception Area

FSHA New Examination Room

FSHA New Exam Room

FSHA Second Floor Conference Room

FSHA Second Floor Conference Room

 

Construction Update
8/16

  • The main entrance is complete.
  • The isolation ward is in progress.
  • The examination rooms are complete.
  • The lobby is nearly complete.

FSHA External View

FSHA External View

FSHA Newly Completed Main EntranceFSHA Newly Completed Main Entrance

FSHA Isolation RoomFHSA Isolation Room

FSHA Examination RoomFHSA Examination Rooms Completed

FSHA Nearly Completed Reception RoomFHSA Reception Room in Progress

Construction Update
Week of 5/30/16

On the outside of the new addition:

  • Work continues¬†on the front lobby addition.
  • The glass has been installed on both levels of the addition.

 

May Exterior - Main Entrance

May Exterior - Side View

May Exterior - Breakroom and Conference Room

 

An inside view of the new addition.

  • Framing and walls continue to be installed throughout the building. Electrical and mechanical work is taking place daily.
  • Painting and interior work continues.
  • HVAC contractors are working on installing the ducts in the new addition that will house the new exam rooms.

May Interior 2

May Lobby 1

 

Isolation Suite:

  • In isolation, the walls have been painted, ceiling installed and a new epoxy floor has been applied last week.
  • The isolation doors and cages are being installed this week.

Isolation Suite